What Happens During Demolition? A Step-by-Step Guide

Articles24 Nov 26

One of the biggest unknowns for Knockdown Rebuild customers is demolition.

What actually happens? Who organises it? How long does it take? And what about asbestos?

Here’s the honest answer: demolition itself is one of the quickest parts of your entire project, often just a few days. It’s the preparation beforehand that takes time, and it’s that preparation that makes everything run safely and smoothly.

Here’s what to expect, stage by stage.

Before demolition: preparation (typically 10-12 weeks)

Long before machinery arrives, there’s important groundwork.

  • Demolition permits are required for every project, confirming the demolition will be carried out safely and legally

  • Abolishing services such as power, gas, sewer and NBN. This process takes a minimum of 4 weeks

  • Temporary fencing  site is secured

  • Asset protection - council requirement that protects public assets like footpaths, kerbs and street trees from damage during works

  • Site inspections and environmental checks completed where required

We’ll refer you to trusted demolition contractors who will help manage this process with you.

What about asbestos?

Many homes in Australia have asbestos. The material used in everything from eaves and fencing to bathroom walls in Australian homes for decades.

This is completely normal, and it’s a routine, well-managed part of the demolition process. Your demolition contractor will manage this for you.

Asbestos removal does add some time and cost to demolition, which is why it’s identified early - so it’s factored into your quote, not discovered as a surprise.

Can I keep anything from my old home?

Yes, and it’s worth thinking about before demolition day.

Many families choose to salvage items with practical or sentimental value. Just remember nothing can be stored on site during the build.

Demolition

Once everything is approved and prepared, demolition can begin.

Heavy machinery carefully brings down the existing structure, and materials are progressively removed from site. Depending on the size and construction of your home, this usually takes between one and three days.

It’s also worth knowing that most demolition materials don’t go to landfill. Concrete and bricks are typically crushed and recycled into road base, and metals are recovered and recycled.

Clearing and preparing the site

Once demolition is complete, the site is cleared of debris, any required levelling is carried out, and final inspections are completed.

Because site conditions often change after demolition, we'll also arrange a new soil test and land survey to confirm the site's levels and engineering requirements before construction begins.

This is an important step that ensures your new home is designed and built to suit the actual conditions of your block. It also means construction doesn't start immediately after demolition, as there's still essential preparation to complete before your slab can be poured.

What affects the cost of demolition?

Demolition costs vary from project to project. The main factors are:

  • Size and construction of your home

    A large double-storey brick home costs more to demolish than a single-storey weatherboard

  • Asbestos

    The amount present and the complexity of removal

  • Site access

    Tight blocks or limited street access can slow the work

  • What else is on the block

    Pools, large sheds, extensive concrete or significant trees add to the scope

Your demolition contractor will walk through all of these things with you.